Subcontractor “pass-through” claims, sponsored by a prime contractor against a public project owner, are both useful and controversial. A pass-through claim results from a claim liquidation agreement between the prime and the sub. The prime agrees to pursue the project owner, at the prime’s expense, for the subcontractor’s increased costs. The prime will pass through the recovery, if any, to the sub. In return, the sub agrees to accept only what the prime is able to recover from the owner and otherwise hold the owner harmless.
Continue reading "Subcontractor "Pass-Through" Claims Still a Matter of Controversy" »
The “total cost method” of quantifying construction claims has always had a bad reputation. The technique compares the cost of the work as bid with the cost of the work as performed and attributes all the cost increase to the acts or omissions of the project owner. It has been considered a bad practice because it is imprecise and it lacks proof of causation by the owner. Now, however, the technique has been resurrected as the “modified total cost method.” And it is enjoying success.
Continue reading "Much Maligned "Total Cost Method" Gets New Life" »
A fIt is well established that when a project owner issues a directive the contractor must comply, even if the contractor considers the directive an expansion or change in the scope of work. The contractor cannot stop work and insist on negotiating a price adjustment. The contractor must rely on the contractual dispute resolution procedures to seek eventual compensation. Some contract documents, however, take advantage of the contractor’s lack of leverage and skew the process in the owner’s favor.
Continue reading "Unilateral Resolution of Unpriced Changes" »
Several months ago we addressed the risk of owner nonpayment. Should the risk be borne solely by the prime contractor who, of course, elected to contract with the project owner? Or should subcontractors share this risk?
The question arises in the context of “pay-if-paid” clauses in subcontracts. The subcontractor gets paid for its work only if the prime contractor receives payment from the project owner for the sub’s work. These clauses are controversial. And their enforceability is increasingly subject to challenge.
Continue reading "Shared Risk of Owner Non-payment" »
There has always been a tension between the right to arbitrate disputes and the right to place a mechanic’s lien on the project owner’s property. Arbitration is a creature of contract. The parties to a construction contract have mutually agreed to resolve their disputes through binding arbitration. As with any contractual right, however, the right to arbitrate can be waived through conduct inconsistent with the assertion of that right.
Continue reading "Tension Between Arbitration and Mechanic's Lien Rights" »
A reader recently raised an interesting question regarding a quantity estimating error and unbalanced bidding. The contractor in question had been quite certain a quantity estimate in a bid schedule was greatly understated. The contractor assigned an inflated unit price to this item, while bidding other items basically at cost. The contractor was awarded the contract, only to have the project owner delete the item with the understated quantity. The reader asked if this was permissible.
Continue reading "Flawed Quantity Estimates and Unbalanced Bidding" »
When a contractor is forced to work out of sequence, in a stop-and start fashion, or in a congested work area, labor costs can skyrocket. Known as “lost productivity” or “labor inefficiency,” this can be a major element in many delay claims. But it is a cost which is difficult to quantify and prove.
Continue reading "Quantifying Lost Labor Productivity" »
While construction contracts usually require the contractor to provide prompt notice of an occurrence giving rise to a claim, the actual adjudication of the claim – the determination of owner responsibility and the recovery of costs – is another matter. Contracts frequently mandate an attenuated process of nonbinding mediation and other administrative procedures. A final decision on the merits of the claim may be years away.
Continue reading "Should Contract Claims Be Consolidated in a Single Action?" »
Many milestones in a construction project are established or acknowledged through certification by a third party designated by the project owner. This individual, stipulated in the construction contract, is typically the project architect or engineer. It may be a different owner’s representative. But the operative word is owner’s representative.
The denial of certification or a delay in certification can be very costly for a contractor. The contractor, however, has very little influence over or leverage with the certifier. The certifier is the agent of the owner with a duty to protect the owner’s interests. The certifier has few obligations to the contractor, possibly just the obligation to avoid bad faith or fraud.
Continue reading "The Role of the Owners Representative" »
Recent Comments